Continue to Site

Welcome to EDAboard.com

Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

[SOLVED] Microsoft Project 2019 dependencies

Status
Not open for further replies.

barry

Advanced Member level 7
Advanced Member level 7
Joined
Mar 31, 2005
Messages
6,555
Helped
1,206
Reputation
2,424
Reaction score
1,434
Trophy points
1,393
Location
California, USA
Activity points
35,655
I've just started playing with MS Project, and already I'm stumped. Maybe this can't be done, but here's what I want:

I've got Task A, Task B and Task C.

When Task A completes, Task B and Task C start. (Finish-to-Start)

Task C can't complete until Task B completes. (Finish-to-Finish).

In other words, Task C has a start dependency and a finish dependency.

Is this doable? How?

I tried linking Task A and Task B to Task C as described, but it seems to just move the end of Task C to the end of Task B(as desired), but the start of Task C moves so that its duration is what's entered in the "Duration " box(not as desired).
 

Solution
Thanks, Susan. You understood exactly what I was trying to do. Your solution worked! I knew I wasn't the first person to ever want to do this, but, boy, they sure made it difficult!!

(Apparently, the dependencies have to be MILESTONES, they can't just be tasks.)
In the 'Precedence' column for C put the task ID for B followed by "FF".
(Sorry for having 2 images - I couldn't find a way to delete the first one to show both the text and the Gantt chart in the one image. )
(I think I have the dependency the way you want it - just put the 'precedence' on the other task if that is the right way around.)
Susan
 

Attachments

  • Capture.PNG
    Capture.PNG
    34.8 KB · Views: 194
  • Capture2.PNG
    Capture2.PNG
    3.7 KB · Views: 198

That doesn't work. I think maybe it LOOKS like yours worked because you had 1day duration for everything. Here's what I got:

1654022459435.png

It still tries to keep task c an whatever duration is specified, and ignores the 1(FS) constraint
 

Ah - now you are starting to realise who project managers get paid the big bucks (if only!!!).
What is happening here is that MS Project sees that you have a 1 day Task C that can occur any time after Task A completes but must finish as Task B completes. Because Tasks B is 5 days but Task C is 1 day, MS Project adds the "slack" this creates before the start of Task C.
As with many things, precise wording is important. What I take it you want is for Task C to be of VARIABLE duration but it must start IMMEDIATELY after Task A ends and COINCIDENT with the end of Task B.
(As Task B can start immediately after Task A - there are no other constraints or dependencies that might allow there to be a gap here - it could be argued that Task B and Task C are in fact the same task. However I can imagine situations where (say) Task B is outsourced to a supplier and Task C is some internal process that monitors the progress of the supplier.)
What you probably want is called a 'hammock task' (because it is joined between to 'fixed' points). Some versions of MS Project allow this and others don't. What you need to do (besides looking up 'hammock task' on Google) is to go into the 'Finish' column cell of the proceeding task (Task A in your case) and copy the date (the standard Ctrl-C). Then go to the 'Start' column cell for the hammock task (Task C in your case) and use the 'Paste Special' to select the 'Paste Link' option. That fixes the start of Task C to the end of Task A.
Next go to the 'Finish' column for Task B and copy that as well, then Paste Link it into the 'Finish' column of Task C. This is the part that probably won't work that well for you depending on your MS Project version.
Ultimately, you may need to link the start of Task C to the end of Task A (using the date copy/paste) and then manually adjust the duration to match Task B.
I've not tried it but you might also try setting the 'Predecessor' setting for Task C to be '1FS+0D, 2FF' which can tell MS Project to force the slack to be 0 days - just a guess.
Susan
 

Thanks, Susan. You understood exactly what I was trying to do. Your solution worked! I knew I wasn't the first person to ever want to do this, but, boy, they sure made it difficult!!

(Apparently, the dependencies have to be MILESTONES, they can't just be tasks.)
 

Solution
Status
Not open for further replies.

Part and Inventory Search

Welcome to EDABoard.com

Sponsor

Back
Top